A federal filing in September to open discussions about a large-scale data center in Bow has grown into an organized campaign against the project. Residents will get their first real chance to weigh in next month.
The town will hold a public hearing on Thursday, Dec. 3, to discuss whether voters should consider an ordinance pausing all data center development within Bow’s municipal boundaries for one year. Residents will have the opportunity to share their opinions on whether the measure should appear on the town warrant.
“I think it’s really important that voters get to have a voice in the process,” said Eleana Colby, a select board member. “This is something that impacts residents. It may have a positive or negative impact on anybody’s financials.”
News of the possible project broke in September, when Granite Shore Power, owner of the shuttered Merrimack Station, asked the Federal Energy Regulatory Commission to open talks with Eversource about connecting a 350-megawatt facility to the regional power grid.
The town is considering an ordinance after receiving a petition signed by 800 residents opposing a data center in Bow.
No New Hampshire law specifically addresses data center moratoriums, although Gov. Kelly Ayotte has publicly spoken about wanting to pursue one.
Instead, the town of Bow is relying on a state statute that allows municipalities to temporarily pause certain development projects while it establishes permanent regulations.
The statute permits these pauses under “unusual circumstances” that affect a municipality’s ability to provide adequate services, require immediate attention and necessitate the development or revision of a growth management plan.
The draft ordinance points to Merrimack Station, the coal-fired power plant that retired in 2024.
It states that the closure raises questions about what happens to the site, the electrical infrastructure and the other resources that served it. The document adds that the site could attract a large energy user such as a data center, one use the town’s zoning ordinance does not currently address.
Bow’s approach to data centers is similar to that of Nottingham, where voters approved a 12-month moratorium on data center development within town limits in September.
The ordinance’s stated purpose is to protect “public health, safety, and welfare of the residents of Bow,” to ensure reliable electricity and adequate drinking water, and safeguard the regional watershed and ecology from the effects of large, resource-consuming development.
Not everyone in Bow opposes the idea, though. Some residents would welcome a data center in hopes it would ease the tax burden. With property tax rates at $20 per $1,000 of assessed value, the town has struggled to find relief, and any significant new source of revenue is appealing.
Data centers are commonly sited at former power plants because these sites have established connections to electric grids, nearby water sources and large tracts of land to support their infrastructure needs.
Merrimack Station and its 343 surrounding acres in Bow check nearly every box, offering plenty of space, proximity to the Merrimack River and an existing connection to the power grid.
The public hearing will be held at 7 p.m. on Dec. 3 in the Bow High School auditorium.